Royal Sovereign House, Chatham

Redeveloping a former office building into a luxury residential block, including strip-out and complete turnkey fit-out.

sector

Residential

cost

< £10 Million

type

Interior Fit-Out

status

Completed

Client & brief

The client took on a large existing commercial building in the heart of Chatham, with a view to repurposing the structure into a residential apartment block. DRG was commissioned as main contractor and work started in May 2021.

Get in touch

What can DRG do for you?

By choosing us, you can be safe in the knowledge that your construction or refurbishment project will be delivered to the highest standard, with low environmental impact.

Whether you are looking for a main contractor for general works or major works, we deliver on time and on budget. Working collaboratively with our clients, we create a built environment that helps communities live, work and grow stronger.

Get in touch

The DRG solution

Formerly an office building, Royal Sovereign House was to be redeveloped into 45 luxury apartments.

A double-height atrium required demolition, with new walls constructed into the existing roof void. New windows were added throughout, and the roof and façade required improvement work, with plant wells infilled. All new above-ground drainage required linking to existing outfalls. The existing undercroft parking was made good, with new bicycle racks added.  

Internally, following strip-out and structural work, partition walls and new doors were installed throughout to create the individual apartments. Each apartment was completed to turnkey standard, with high-specification kitchens and bathrooms and performance flooring throughout.

Key features

  • Complete strip-out
  • New glazing
  • Roofing works
  • Façade works
  • Internal partitioning and refurbishment
  • Electrics, connectivity and plumbing
  • External works, lighting and access
  • Cycle stores

The result

The project was completed in October 2022. In line with our carbon offsetting partnership with Ecologi, the project led to the planting of 100 trees.

Project specification